planning_effort
points from resolved FE epics to derive a time-per-point scalar, then applies it to remaining work.
| Project start | Jan 05, 2026 |
| Days elapsed | 227 |
| Resolved FE epics | 13 |
| Calendar velocity | 0.0573 epics/day |
| Remaining epics | 17 |
| Cal. completion | 297 days from now |
| Resolved effort sum | 229 pts (13 epics) |
| Days per point | 0.991 days/pt |
| Remaining effort | 278 pts (17 epics) |
| Est. days (sequential) | 223 days |
| Weighted completion | Mar 31, 2027 |
| Epic | Effort pts |
|---|---|
| Review tool | 40 |
| Input Navigator | 40 |
| Inline profiling | 5 |
| Audit | 13 |
| Content Preview | 13 |
| Notifications | 13 |
| Recipe Management | 40 |
| Advanced Search | 13 |
| Version Control | 13 |
| Content Lifecycle | 13 |
| Administrator tools | 13 |
| Table Content Transformer | 13 |
| Adj. days/pt | 0.991 |
| Sequential days | 223 days |
| Est. completion | Mar 31, 2027 |
| Epic | State | Pts | Est. duration | Standalone finish | Sequential finish |
|---|---|---|---|---|---|
| Comparison Tool | Active | 13 → 6 rem. | 6 d | Aug 26, 2026 | Aug 26, 2026 |
| Reuse analyser | Active | 13 → 6 rem. | 6 d | Aug 26, 2026 | Sep 01, 2026 |
| Integrated editor | Active | 40 → 20 rem. | 20 d | Sep 08, 2026 | Sep 21, 2026 |
| Release Manager | Active | 40 → 20 rem. | 20 d | Sep 08, 2026 | Oct 11, 2026 |
| Analytics & Business intelligence | New | 5 | 5 d | Aug 25, 2026 | Oct 16, 2026 |
| Component reuse | New | 5 | 5 d | Aug 25, 2026 | Oct 21, 2026 |
| PDF publishing | New | 5 | 5 d | Aug 25, 2026 | Oct 26, 2026 |
| Hotspot editor | New | 13 | 13 d | Sep 01, 2026 | Nov 08, 2026 |
| Migration analyser | New | 13 | 13 d | Sep 01, 2026 | Nov 21, 2026 |
| Import module | New | 13 | 13 d | Sep 01, 2026 | Dec 04, 2026 |
| Relationships Visualizer | New | 13 | 13 d | Sep 01, 2026 | Dec 17, 2026 |
| Info Designer | New | 13 | 13 d | Sep 01, 2026 | Dec 29, 2026 |
| Draft creator | New | 13 | 13 d | Sep 01, 2026 | Jan 11, 2027 |
| PDF to XML converter | New | 13 | 13 d | Sep 01, 2026 | Jan 24, 2027 |
| Reuse Suggestions | New | 13 | 13 d | Sep 01, 2026 | Feb 06, 2027 |
| Terminology checker | New | 13 | 13 d | Sep 01, 2026 | Feb 19, 2027 |
| Translation management | New | 40 | 40 d | Sep 28, 2026 | Mar 31, 2027 |